Vol. 58 No. 4
April 2006
Novel well-completion techniques and exceptional field execution allowed the six well completions in the Marco Polo deepwater tension-leg-platform (TLP) project to be accomplished in world-class fashion. All six wells (17 frac packs) were placed on production in only 168 days, including 14 days lost because of storms. The full-length paper focuses on how the implementation challenges of completing 17 zones in six deepwater dry-tree wells with a 1,000-hp rig were met and highlights a number of concepts and technical firsts that can be used in other deepwater development projects.